[Home]
[Wolfe Tile Plow]
[Tile Survey Polaris]
[Sample Tile Map]
[Sample Tile Easement]
[Feedback]             [Dappert Office Hours]
[History]
[Favorite Links]
[Tile Stringer Truck
[Need a stencil Cut?]
Websites made by: John Dappert:

Lincolnland Agri-Energy

 

Articles written by: John Dappert:

E-mail Address: illinoisjohn@mchsi.com

 

Wolfe Tile Plow

Click on picture to enlarge.

The Wolfe tile plow 2003 Tile Wolfe Plow 4.jpg (175883 bytes)used by the Frey Excavating and Drainage team was the core of their tiling operations.  It is a massive machine setting on an extended Cat excavator undercarriage 2003 Tile Wolfe Plow 5.jpg (233316 bytes)and powered by 400 Cat horses, which is difficult to bog down under even the most extreme conditions.  Elevation of the tile is important, any changes in grade can ruin an otherwise good tile system.  The big advantage of this large machine is its ability to keep grade.  When laying large mains, 2003 Tile distant view and Case Track tractor.jpg (130366 bytes)there were a couple of times that running six feet deep with a ten-inch tile boot2003 Tile Plow large boot.jpg (176212 bytes) began to test the ability of the plow to continue forward progress.  On smaller machines, sometimes this is a problem, as the angle of the plow laying the tile can change as the power transfer device begins to spin or dig out.  If the angle of the plow changes, the grade can be compromised, leaving low places in a main that might make it difficult for water above that point to drain easily to the outlet.  Under these conditions, the large track undercarriage started to dig straight down, rather than dig in at the back which would change the angle of the tile installation.  The laser system quickly compensated for these changes, until the plow could work through these difficult conditions.  A smaller plow would have been challenged during these conditions, but it hardly affected this professional designed $350,000 machine.2003 Tile Wolfe gauges.jpg (123753 bytes)

The laser controls 2003 Tile Wolfe Spectra Specialist laser control in cab.jpg (166423 bytes)are monitored constantly as they automatically established grade, to make sure they are operating correctly.  At the end of a lateral run, the laser could be manually overrode so depth was consistent with good drainage.  As we watched the laser controls as the machine was operating, brief blips of lights on the controls would flash to show the corrections either in an upward or downward direction.

Frey Excavation had two tile boots 2003 Tile main beginning.jpg (254184 bytes)for this plow that they carried on a self-designed trailer.  2003 Tile boot trailer.jpg (168380 bytes)One was for 4-6" tile, the larger could lay 8-12" tile.  In many instances the larger main tiles are layer by their wheel excavator, which can detect previous tile which might affect the operation of the new tile field.  If any previous tile are left in the field, they can hinder the new tile from working properly.  If larger mains are needed, the wheel excavators, which take more time to work and cover, can be used.

Watching the plow lay laterals was interesting.  The machine seemed to  move without effort through the field, 2003 Tile Wolfe Plow 2.jpg (165524 bytes)covering the tile with disks during the trip across the lateral line.  First, a trench is dug with a backhoe opening up an access2003 Tile beginning 20001.jpg (280019 bytes) to the main, 2003 Tile First run on East Side of Windmill 40, Main.jpg (193694 bytes)then the tile plow backs the boot into this opening.  the 4" tile is inserted through the boot, 2003 Tile Boot on plow 2.jpg (257445 bytes)2003 Tile main opening into No Business creek.jpg (237875 bytes)and the plow begins to work through the field.  2003 Tile lateral run.jpg (247039 bytes)As the plow moves away, an operator drills a hole in the main, 2003 Tile connections 5.jpg (213849 bytes)and attaches the lateral. 2003 Tile cutting hole in main to attach lateral.jpg (225641 bytes) 2003 Tile connecting lateral to main.jpg (209576 bytes)A plug 2003 Tile end cap terminator.jpg (199004 bytes)at the far end of the lateral keeps dirt from entering the opposite end of the lateral run.2003 Tile distant view of equipment.jpg (190183 bytes)

2003 Tile Beehive inlet cover closeup.jpg (131349 bytes)The yellow cone shaped object made of plastic covered wire is called a beehive inlet.  It was placed above the surface to allow surface water to enter the tile system when the tile was close to a very low place or a ditch.  The objective was to get any surface water into the system as soon as possible, so it could be discharged through the outlet before the seep water entered the system.  It also acted like a vent for the system.  All tile drainage systems need a vent for air to enter, so they are able to "breath" to better allow movement of water in the mains.  2003 Tile Vent riser on corner of crawford.jpg (188241 bytes)The orange tower on the left is referred to as a Higginbotham riser, while it can also allow surface water to enter the tile, it is used more as an air vent in systems designed by Joe and Mike Frey.

To continue, click on Tile Stringer Truck .

Hit Counter

Home ] [ Wolfe Tile Plow ] Tile Survey Polaris ] Sample Tile Map ] Sample Tile Easement ] Feedback ] [ Dappert Office Hours]   [History]   [Favorite Links]  Choosing the right Tractor [Honda Big Red for sale][Tile Stringer Truck] Articles by John Dappert:  [The Squeaky Wheel [Moonshine, Illinois]   [A Fathers Day Message] [February 9, 1954] [10 Must have tools]. E-mail Address:    [ illinoisjohn@mchsi.com ]